Murray Morgan Bridge scheduled to close for re-cabling project Feb. 1

Re-cabling work on the Murray Morgan Bridge will begin today and the bridge will be closed to pedestrians. While closed, the bridge will be braced in the upright position for the cables to be removed and replaced. The stairs to Dock Street will remain open.
The work is expected to take six weeks and the bridge is tentatively scheduled to re-open for pedestrian use in early April. The work is being done in partnership between the City and the Washington State Department of Transportation.

For more information, visit the City’s Murray Morgan Bridge project Web site at http://www.cityoftacoma.org/MMB .

– – – – – – – – – – – – – – – – – – – – – – – – – – – – – –

For earlier Index coverage of the Murray Morgan Bridge, click on the following links:

Steel cables, heavy equipment signal beginning of Murray Morgan Bridge rehab (01/25/10) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1703315&more=0

Bridge Support: A chorus of praise for saving Murray Morgan Bridge (12/04/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1675336&more=0

Tacoma City Council approves Murray Morgan Bridge agreement (12/02/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1673461&more=0

City Council to vote Dec. 1 on Murray Morgan Bridge agreement (11/25/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1669624&more=0

Tacoma closer to owning Murray Morgan Bridge (11/19/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1666253&more=0

Murray Morgan Bridge rehab delayed (10/08/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88=23&id=1638707&more=0

Contract awarded for Murray Morgan Bridge cable project (06/17/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1571549&more=0

City, State Murray Morgan Bridge funding negotiations will continue (05/06/09) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1543929&more=0

Murray Morgan Mojo: $3 million project to replace bridge cables ready to begin (12/16/08) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1453283&more=0

City, State consider innovative financing plan for Murray Morgan Bridge rehab (12/11/08) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1450307&more=0

2008 Washington State Endangered Historic Properties — Murray Morgan Bridge (06/11/08) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1240070&more=0

Murray Morgan Bridge’s Endangered Legacy (05/30/08) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1230053&more=0

Murray Morgan Bridge tops list of Washington Trust’s annual Most Endangered Historic Properties (05/27/08) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1226325&more=0

Murray Morgan Bridge closure expensive decision (10/31/07) — http://tacomadailyindex.com/portals-code/list.cgi?paper=88&cat=23&id=1094891&more=0